Vue de la page 4
Moving the Load Fame
MTS Criterion™ Series 60 Lifiting and Moving Instructions
5
Moving the Load Fame
Unloading
The customer will be responsible for all the unloading process if no Unloading
Service is purchased. In case of special agreement, an MTS field service engineer
can monitor the unloading, storage, and transportation process.
To unload the load frame:
1. Unload the load frame with reference to the lifting position marker
and the gravity center marker .
2. Choose suitable slings according to the weight table.
3. Lift the crate with suitable slings as shown in the following figure.
4. Pay attention to the gravity center marker on the crate to ensure stable
and balanced lifting.
Note If the machine will not be installed right away, store it in a steady, dry and
corrosion free place. MTS is not responsible for damages caused by
improper storage.